Bezpečnosť na prvom mieste: Nehorľavá výhoda VRFB pri skladovaní energie 

S ohľadom na transformáciu klasickej energetiky smerom k čoraz častejšiemu využívaniu elektriny z obnoviteľných zdrojov, sa bezpečnosť systémov skladovania energie stáva čoraz dôležitejšou ruka v ruke s potrebou inštalácií takýchto systémov. Vanádiové prietokové redox batérie (Vanadium Redox-Flow Batteries – VRFB) vynikajú nielen svojou účinnosťou, ale aj výnimočným bezpečnostným profilom, najmä v porovnaní s inými technológiami […]

SAFETY FIRST: THE NON-FLAMMABLE ADVANTAGE OF VRFBs IN ENERGY STORAGE 

As the world transitions to renewable energy, the safety of energy storage systems has become paramount. Vanadium Redox-Flow Batteries (VRFBs) stand out not just for their efficiency but for their exceptional safety profile, especially when compared to other energy storage technologies.  Non-Flammable and Environmentally Friendly  One of the most significant safety advantages of VRFBs is […]

Kysucké Nové Mesto

BESS installed and in the process of installation:
Customer Location MW MWh Provided service Commissioning
INO-HUB Energy SK1- Kysucké Nové Mesto 1,5 2,4 BESS Delivery, Ancillary services 03/2024
INO-HUB Energy SK2- Kysucké Nové Mesto 2,0 2,4 BESS Delivery, Ancillary services 03/2025

Nováky

BESS successful in the tender, pending contract signing:
Customer MW MWh Provided service Expected commissioning
N/A 55,0 BESS Delivery 02/2026

Košice

BESS installed and in the process of installation:
Customer Location MW MWh Provided service Commissioning
INO-HUB Energy SK3 Košice 8,0 10,4 BESS Delivery, Ancillary services 12/2025

Hungary

BESS in tender:

CustomerMWMWhProvided service
N/A3,215,0BESS Delivery, Ancillary services
Other Projects 50,0BESS Delivery, Ancillary services, Flexibility
Summary values 65,0 MWh 

Czech Republic

BESS in tender:

CustomerMWMWhProvided service
N/A8,010,0Delivery and operation of BESS
Summary values 10,0 MWh 

Šaľa

BESS successful in the tender, pending contract signing:
Customer MW MWh Provided service Expected commissioning
N/A 6,0 7,6 BESS Delivery 11/2025