PARTICIPATION IN CONFERENCE ENERGOFORUM 2024

This year, the 18th edition of ENERGOFÓRUM conference once again brought together the most current issues in the energy sector into a single event. The conference was held on October 24–25, 2024, in the Low Tatras and attracted nearly 350 experts, representatives of state institutions, as well as representatives of the private and academic sector.

INO-HUB Energy was one of the two lead partners of the ENERGOFÓRUM 2024 conference, and our Chairman of the Board and CEO, Rudolf Sihlovec, actively participated in expert discussions as a panelist in Electrification 2.0: The Challenges of Sector Transformation. Together with other experts, he analyzed key issues related to electrification, innovation, and the future of the energy sector.

The full discussion on Electrification 2.0: The Challenges of Sector Transformation can be found on the official event website (available only in Slovak): https://www.energoforum.sk/sk/konferencie/energoforum-2024/videa/?dc=96EF33421

We are pleased to have been part of this conference, which opens up a space for expert discussions every year. We highly appreciate the inspiring presentations, interactive discussions, and networking opportunities that create ideal conditions for shaping the energy sector in Slovakia and in the broader European context. We look forward to the next edition.

You can find additional information about this conference on their official web page: https://www.energoforum.sk/sk

ACKNOWLEDGEMENT:

This work was supported by the project: IPCEI_IE_FLOW_BESS_012021_2. phase

Kysucké Nové Mesto

BESS installed and in the process of installation:
Customer Location MW MWh Provided service Commissioning
INO-HUB Energy SK1- Kysucké Nové Mesto 1,5 2,4 BESS Delivery, Ancillary services 03/2024
INO-HUB Energy SK2- Kysucké Nové Mesto 2,0 2,4 BESS Delivery, Ancillary services 03/2025

Nováky

BESS successful in the tender, pending contract signing:
Customer MW MWh Provided service Expected commissioning
N/A 55,0 BESS Delivery 02/2026

Košice

BESS installed and in the process of installation:
Customer Location MW MWh Provided service Commissioning
INO-HUB Energy SK3 Košice 8,0 10,4 BESS Delivery, Ancillary services 12/2025

Hungary

BESS in tender:

CustomerMWMWhProvided service
N/A3,215,0BESS Delivery, Ancillary services
Other Projects 50,0BESS Delivery, Ancillary services, Flexibility
Summary values 65,0 MWh 

Czech Republic

BESS in tender:

CustomerMWMWhProvided service
N/A8,010,0Delivery and operation of BESS
Summary values 10,0 MWh 

Šaľa

BESS successful in the tender, pending contract signing:
Customer MW MWh Provided service Expected commissioning
N/A 6,0 7,6 BESS Delivery 11/2025